Concrete volume calculator
Each dimension carries its own unit, so you can enter a slab as 4 m × 3 m × 100 mm without converting anything by hand. The result comes in cubic metres, feet and yards, because ready-mix is ordered in different units in different markets.
Use this for several matching footings or columns.
Covers spillage, over-excavation and uneven subgrade. Site conditions decide the figure.
In litres of mixed concrete, from your bag label. Yields differ by manufacturer and mix, so there is no default.
Result
- Volume with allowance
- 1.32 m³
- Volume
- 1.2 m³
- In cubic yards
- 1.726 yd³
- In cubic feet
- 46.62 ft³
- In litres
- 1,320 L
How this is calculated
Every dimension is converted to metres before multiplying. Mixing units without converting them first is the single most common way this calculation goes wrong, and it produces an answer that is wrong by a factor of ten or a thousand rather than by a little.
- depth
- — slab thickness, or footing depth
- quantity
- — how many identical elements you are pouring
- waste
- — the allowance you add for losses on site
Worked example
A patio slab 4 m long, 3 m wide and 100 mm thick is 4 × 3 × 0.1 = 1.2 m³. With a 10% allowance you would order 1.32 m³, which is 1.73 cubic yards or 1,320 litres. If you were bagging it by hand with a mix yielding 12.5 litres per bag, that is 106 bags — which is also a good argument for ordering ready-mix at this size.
How to use it
- Enter length, width and depth, each with its own unit. Depth in millimetres alongside metres is fine.
- Set the number of identical elements if you are pouring more than one footing or column of the same size.
- Add a waste allowance appropriate to the site, then read the volume in whichever unit your supplier quotes.
- Only enter a bag yield if you are mixing from bags; leave it blank for ready-mix.
Limitations and assumptions
- This models rectangular shapes only. Circular columns, tapered footings, steps and slabs on a slope need to be broken into rectangular parts and added up.
- Bag yield has to come from your own bag. It varies by manufacturer, mix and how wet you make it, so a built-in default would be a guess presented as a fact.
- The waste allowance is yours to choose. The right figure depends on the subgrade, the formwork and how the concrete is placed; this tool does not recommend a number.
- No reinforcement, no sub-base and no formwork are included, and the volume makes no claim about the strength class or mix design you need.
Questions
How many cubic metres is my slab?
Multiply length by width by thickness, all in metres. A 4 m × 3 m slab at 100 mm thick is 4 × 3 × 0.1 = 1.2 m³. The trap is the thickness: 100 mm is 0.1 m, not 100, and getting that wrong inflates the answer a thousandfold.
Why does the result show cubic yards as well?
Because ready-mix concrete is ordered by the cubic yard in the United States and by the cubic metre almost everywhere else. One cubic metre is about 1.308 cubic yards.
How much waste should I allow?
That depends on the job, and this tool will not invent a figure for you. Ask your supplier what they see on comparable pours — an uneven subgrade or hand-placing both push it up, and running short mid-pour is far worse than ordering a little over.
Can I use this for a circular column?
Not directly — it multiplies three straight dimensions. For a circle, work out π × radius² for the area and multiply by the height separately, or enter an equivalent rectangle of the same cross-sectional area.
Related calculators
- Gravel calculatorVolume of gravel, sand or aggregate for an area at a given depth, in cubic metres, feet and yards, with weight if you supply a bulk density.
- Tile calculatorHow many tiles a floor or wall needs, with the grout joint included in each tile's footprint and whole boxes worked out.
- Paint calculatorPaint needed for a room: wall area from the dimensions, doors and windows subtracted, coats and spreading rate applied.
This page has not yet had an editorial review.
